Tax Planning for Construction and Installation Enterprises after the Replacement of Business Tax with Value-Added Tax

2026-08-25

The construction project contracting tells you: According to the Notice of the State Administration of Taxation on Comprehensively Launching the Pilot Program of Replacing Business Tax with Value-Added Tax (Cai Shui [2016] No. 36), the tax rate for providing construction services is 11%; in addition, if the following conditions are met, the simplified tax calculation method may be chosen, with a levy rate of 3%:

1. General taxpayers providing construction services on a labor-only basis may choose to apply the simplified tax calculation method.

Providing construction services on a labor-only basis means that the construction party does not purchase the materials required for the construction project or only purchases auxiliary materials, and collects labor fees, management fees, or other fees for the construction services.

Construction engineering contracting

2. General taxpayers providing construction services for owner-supplied projects may choose to apply the simplified tax calculation method.

An owner-supplied project refers to a construction project where all or part of the equipment, materials, and power are purchased by the project owner.

3. General taxpayers providing construction services for old construction projects may choose to apply the simplified tax calculation method.

An old construction project refers to:

(1) A construction project where the contract start date indicated in the Construction Project Construction Permit is before April 30, 2016;

(2) For projects without a Construction Project Construction Permit, a construction project where the start date indicated in the construction project contract is before April 30, 2016.

According to the above provisions, after the replacement of business tax with value-added tax, if your unit meets the conditions for applying the simplified tax calculation method, it will not lead to an increase in tax burden.